A Maintenance Frame For Sishen Iron Ore
- JAD Engineering
- Nov 21, 2020
- 1 min read
Updated: Nov 19, 2022
Our client was doing maintenance on their DMS crusher shafts. Because no work under a suspended load is allowed, we had to develop a concept design where maintenance could proceed without endangering the artisan.

We designed a platform that can accommodate three different sizes of eccentric shafts - 110t, 70t, and 13t. For the small 13t shaft, we added an insert frame that makes it possible to lower the shaft for access from the floor.
Incorporated into this design is a platform to work on the bottom part of the shaft and a trolley to handle the 300kg thrust bearing on the bottom of the shaft.
Working as a team, our engineers and drawing department came up with this great solution to meet our client's needs.
Some pictures after the manufacturing phase of this project.