WEC CONTAINER PLANTS
Client
WEC Projects
Project Duration
2 Months
Sector
Wastewater Treatment, Mechanical Engineering​
Standards
National Water Act 36 of 1998
JAD partnered with WEC Projects to deliver four modular wastewater treatment plants in Guinea, comprising one 250 m³/day plant, one 150 m³/day plant, and two 60 m³/day plants. The project covered the process, mechanical, electrical, piping, and instrumentation disciplines.
​
Detailed 3D models were developed to coordinate piping, cabling, instrumentation, and support structures, eliminating design clashes and facilitating efficient fabrication. Comprehensive manufacturing drawings supported the prefabrication and installation of the containerized units, ensuring seamless assembly and successful project execution.